Thursday, April 29, 2010

Scaffolding going up ...


The scaffolding has been put up this week..and that's about it.
The windows haven't been replaced as I was told they would be 2 weeks ago!
I'm giving a call my SS tomorrow to check what's going on.

L'echafaudage est en place...
Les fenetres n'ont pas encore ete changees comme promis...

Brickwork pics from last week




Monday, April 19, 2010

Brickwork has started !

Brickwork has started today... Here are some small videos (from an ipod!), I didn't have my camera with me... The start of the brickwork looks good (much better in real than on the video! lol)

Ils ont commence a monter les briques... Voila quelques petites videos de tres mauvaise qualite (de mon ipod), j'avais pas mon appareil photo avec moi. Ca rend mieux en vrai que sur la video je dois dire...






This is an off white mortar... Hopefully... when it dries out !!!

Les joints des briques sont censes etre blancs... On espere que la couleur blanche va apparaitre quand ca va secher!

Sunday, April 11, 2010

Windows up... and bricks delivered!


We've had the bricks delivered!! Which is very good as the weather forecast for next week is good! :-)

On a recu la livraison des briques, ils pourront demarrer la pose la semaine prochaine, puisque la meteo est bonne!! :-)

The windows are being installed, only 3 to go... :-)

We have noticed 3 little problems about the windows:
- 1 Window is already broken (in the kitchen)
- 1 Window installed is not double glazed as requested
- 1 Window on the ground, about to be installed is not double glazed neither.

Les fenetres ont ete installees, il n'en manque que 3 a poser.
On a remarque 3 petits problemes par rapport aux fenetres:
- Une est cassee
- Une posee n'est pas double vitrage.
- Une au sol qui va etre posee n'est pas double vitrage.











Wednesday, April 7, 2010

Back to work!


The long week-end is behind, and we have the windows delivered.
They've also started to put the enviroseal foil, which will go all around the house on the 2 levels, and also under the roof.
It's been raining on and off, which doesn't help!

Les travaux ont repris.
Les fenetres ont ete livree, et vont etre posees tres bientot. C'est du double vitrage, j'ai verifie!!
Le truc vert que vous voyez, c'est une extra protection qu'on a demande... cela ameliorera un peu l'isolation en protegeant la laine de roche contre l'humidite, et evitera la condensation a l'interieur...
Il pleut pas mal en ce moment...dommage...





Saturday, March 27, 2010

Delays...

We've received the building inspector report last week and we have 3 items requiring attention:

- The 90mm timber frame overhangs the concrete 30mm between the dining room and the leisure room. Additional support is required. Design to be by an engineer.

- The 90mm external kitchen/dining room wall overhangs the concrete slab up to 20mm. Additional support is required.

-The junction of the timber frame in the corner of the dining/leisure rooms has not been blocked and needs timber blocks or pressed metal angles installed.

Otherwise the frame is good.
I talked to my SS and he told me that he would fix those 3 items (just checked today, they're not fixed yet).


Also, we have a brick delivery delay (for some reason, Boral can't supply in time), we should get them beginning of April!

Plus.... Windows supplier has made a huge mistake with our windows...They have to make them all again!

So, there we go ... we're waiting, but are confident that Wisdom will make up the time (a shame, the weather has been so good lately!!!!)


Pas grand chose de neuf, la construction prend un peu de retard parcequ'ils nous ont fabrique les mauvaises fenetres, et que les briques ne sont pas disponibles avant le debut du mois d'avril.
Ca devrait donc bouger pas mal au mois d'avril quand tout est rentre dans l'ordre... Pour l'instant, on attend...



Saturday, March 20, 2010

Gas and pipes


Since the 16/03/2010, a few things have been added....

Depuis le debut de la semaine, voila ce qui a ete ajoute...




Well, last Monday I notified our SS about the overhanging problem, and he told me that he would check with engineers if it needs to be fixed. I haven't received a call or an update, I have on the other hand received the invoice for the frame stage (which is obviously not finished according to The Australian Building Code).
Our independent inspector will let us know what still needs to be done next week (Hopefully monday).

I can see on www.forum.homeone.com.au that other builders give frequent updates about the construction (at least the starting dates of big stages), well....so far for us, we haven't received one single call, unless we call!

Nowadays, with mobiles and internet, it's really a bad image for the builder...
If you live far from your house being built, it must be hard and frustrating to know what's going on on your land...(lucky for us, we live close).