We've received the building inspector report last week and we have 3 items requiring attention:

- The 90mm timber frame overhangs the concrete 30mm between the dining room and the leisure room. Additional support is required. Design to be by an engineer.

- The 90mm external kitchen/dining room wall overhangs the concrete slab up to 20mm. Additional support is required.

-The junction of the timber frame in the corner of the dining/leisure rooms has not been blocked and needs timber blocks or pressed metal angles installed.

Otherwise the frame is good.
I talked to my SS and he told me that he would fix those 3 items (just checked today, they're not fixed yet).


Also, we have a brick delivery delay (for some reason, Boral can't supply in time), we should get them beginning of April!

Plus.... Windows supplier has made a huge mistake with our windows...They have to make them all again!

So, there we go ... we're waiting, but are confident that Wisdom will make up the time (a shame, the weather has been so good lately!!!!)


Pas grand chose de neuf, la construction prend un peu de retard parcequ'ils nous ont fabrique les mauvaises fenetres, et que les briques ne sont pas disponibles avant le debut du mois d'avril.
Ca devrait donc bouger pas mal au mois d'avril quand tout est rentre dans l'ordre... Pour l'instant, on attend...